Event 1302

Event 1302 — Waiting for grid voltage / Grid connection installation failure

SMA · SUNNY BOY SMART ENERGY Inverters

What does Event 1302 mean?

The inverter displays a grid connection error, indicating it is waiting for grid voltage or there is an installation failure. This typically means either the Live (L) or Neutral (N) conductor is not connected, or the utility grid itself has failed.

Common Causes

  • Utility grid failure or power outage.
  • Line conductors (L or N) are not correctly connected.
  • Miniature circuit breaker for the AC connection is switched off.
  • AC cable is damaged or incorrectly connected.

Repair Steps & Checklist

Click steps to track your progress.

  1. 1

    Check if there is a general power outage or utility grid failure in your area.

  2. 2

    Verify that the line conductors (L and N) are securely connected to the inverter's AC terminal.

  3. 3

    Ensure the miniature circuit breaker for the inverter's AC connection is switched on.

  4. 4

    Inspect the AC cable for any visible damage and confirm it is connected correctly at both ends.

  5. 5

    If the issue persists after these checks, contact a qualified electrician or SMA Support.

Browse all codes in this manual (28)
Verified technical data. Last updated: April 2026

Related Faults

AFCI tripped (5 arcs)AFCI tripped (5 arcs) — Inverter feed-in permanently interruptedAll 3 LEDs solidAll 3 LEDs solid — Inverter update or booting procedureBlue LED fast flashBlue LED flashing fast — System Manager requesting inverter identification
Source: SMA SUNNY BOY SMART ENERGY Inverters
Open Manual (Page 95)Search more codes in this manual